An August 2017 review identified that Montalbo Nursery and Primary School would benefit from a four classroom extension, an extension to the main hall, the provision of a new staff room, library and group room, and an increase in the number of staff WCs and accessible WCs within the school. The nursery also required an additional classroom and WCs to accommodate a further 30 nursery/reception age children.
This £1.8m project was undertaken by our Construction Services Team, who commenced on site in April 2018. Throughout the project, the school has remained fully occupied. By September 2018 we had completed the classroom extensions as part of Phase 1, and in February 2019 completed the remaining works as part of Phase 2.