Fantastic progress has been made onsite at the Morrison Busty Depot, this is one of the current major projects our construction division are working on. The site compound has been positioned and completed, the excavation for the reduce levels have also been completed along with the stoning up to the required levels.
The site set up and the enabling works have been completed to the proposed works to building blocks C & D, the asbestos removal to both C&D has been completed. Demolitions works has been completed, the removal of windows in the areas where they are to be bricked/ blocked up has been completed.
Electrical strip out, partition walls, first and second fix M&E works are well progressed. The project in regard to the internal refurbishment works is on programme to office blocks C & D with finishing touches such as Tea Points, Skirting, Back Moulds etc done in preparation for further trades to follow, the lift is also now in place.
The erection of the steel frame has commenced on the 27th April
This is an exciting Project and we look forward to sharing further updates soon!