Montalbo Primary School

Montalbo Primary School, drone image
July 2018 - drone image of the whole Montalbo Primary School
Montalbo Primary School, drone image of the roofing works
July 2018 - drone image of the roofing works
Montalbo Primary School, internal works progressing on programme
July 2018 - internal works progressing on programme
Montalbo Primary School, extension works nearing completion
August 2018 - Phase 1 extension works nearing completion.
Montalbo Primary School, roofing works progressing on programme
September 2018 - roofing works progressing on programme
Montalbo Primary School, internal works completed
December 2018 - internal works completed so hall could be used for the school play.
Montalbo Primary School, ongoing works
February 2019 - internal works nearing completion
Montalbo Primary School, external works nearing completion
February 2019 - external works nearing completion
Montalbo Primary School, internal works complete and classroom ready for use
February 2019 - internal works complete and classroom ready for use.
Prev
Next

An August 2017 review identified that Montalbo Nursery and Primary School would benefit from a four classroom extension, an extension to the main hall, the provision of a new staff room, library and group room, and an increase in the number of staff WCs and accessible WCs within the school. The nursery also required an additional classroom and WCs to accommodate a further 30 nursery/reception age children.

This £1.8m project was undertaken by our Construction Services Team, who commenced on site in April 2018. Throughout the project, the school has remained fully occupied. By September 2018 we had completed the classroom extensions as part of Phase 1, and in February 2019 completed the remaining works as part of Phase 2.

Primary Sidebar

Contact us

New customers:

03000 269 359

dsbd@durham.gov.uk

  • Legal information
  • |
  • Accessibility Statement
  • |
  • Contact
  • |
  • Mailing list
  • |
  • Useful links
  • |
  • A to Z
  • Facebook Logo
  • Twitter Logo
  • Instagram Logo
We understand the critical role schools, academies and other public sector organisations have in the fight against COVID 19. As a result of national guidance, many of our staff are working from home but are available to support customers via telephone, conferencing, portal or email. We may have to reduce support in some non-essential areas, therefore, if you are unable to contact us through your normal communication channels, you can contact us through our Customer Services Helpdesk on 03000 26 0000 or by email commercialservices@durham.gov.uk
Dismiss